Construction Updates

Q1 - 2025

The North Building and East building have reached full height and have commenced interior framing and window installation.  The South Building has ascended to the 7th Residential Floor.

Q1 - 2025

The North Building and East building have reached full height and have commenced interior framing and window installation.  The South Building has ascended to the 4th Residential Floor.

Q4 - 2024

The North Building has reached full height and has commenced interior framing and the East Building has ascended to the 7th Residential Floor. The South Building has ascended to the 2nd Residential Floor.

Q4 - 2024

The North Building  has reached full height and the East Building has ascended to the 5th Residential Floor. The South Building is progressing beyond the parking levels and approaching the 1st Residential Floor.

Q3 - 2024

Construction of 7th Residential Floor Shell in North Building And 2nd Residential Floor Shell in East Building.  Assemblage of 3rd crane for South Building.

Q3 - 2024

Construction of 6th Residential Floor Shell in North Building

Q3 - 2024

Construction of 2nd Residential Floor Shell in North Building | Garage Level Shells in North Building completed and Nearing completion in East Building

Q2 - 2024

Construction of 1st Residential Floor Shell in North Building | Upper and Lower Garage Level Shells in North and East Building | South Tower Pillars

Q2 - 2024

Construction of Elevator Pits and Foundation

Q2 - 2024

Rebar Framework

Q1 - 2024

Construction of Crane Foundations and Cranes Assembled

Q4 - 2023

Final Site Preparation for Construction