Exterior construction is nearing completion with windows and balcony railings steadily advancing. Inside, walls and finishes are taking shape. On the upper-level amenity deck, the planters for the putting green, yoga lawn, and expansive private terrace residences are being poured.
Q2 - 2025
Window and door installation is nearly complete in the North Building, well underway in the East Building and set to begin in the South Building. Stucco application and painting has commenced on the North building exterior. Interior Drywall and tile is fully underway.
Q1 - 2025
The North Building and East building have reached full height and have commenced interior framing and window installation. The South Building has ascended to the 4th Residential Floor.
Q4 - 2024
The North Building has reached full height and the East Building has ascended to the 5th Residential Floor. The South Building is progressing beyond the parking levels and approaching the 1st Residential Floor.
Q3 - 2024
Construction of 2nd Residential Floor Shell in North Building | Garage Level Shells in North Building completed and Nearing completion in East Building
Q2 - 2024
Rebar Framework
Q1 - 2024
Construction of Crane Foundations and Cranes Assembled